Fuel Switching and SV Considerations - Main - Fall 2015 User Group

In the second quarter of 2015 Minnesota Power’s Laskin Energy Center ceased coal operations and converted the fuel source to natural gas. During the conversion outage, a team of compliance staff and technicians completed an overhaul of the plant’s continuous emission monitoring systems. As the nation’s energy production shifts away from coal, other utilities are undergoing or facing similar projects. Come and hear the details and learn from their experiences.

Presented by R Peterson, ALLETE

These are the slides from a technical breakout session presented at the Fall ESC User Group meeting held in San Antonio, Texas, November 11 & 12, 2015. All ESC customers with current maintenance contracts are members of the user group, with meetings held twice a year, each Fall and Spring. Learn more about the ESC User Group.

11/20/2015 4:00:26 AM